US 41 has been under construction by the Florida Department of Transportation (FDOT) for several years.

These improvements included adding medians and traffic separators as part of a safety improvement.

The CRA and City desire to beautify these medians through landscaping and irrigation. On Jan. 24, 2024, the CRA approved a supplemental task authorization, in the amount of $72,000.00, with RVi Planning Landscape Architecture who will provide for a FDOT compliant landscape and irrigation design to be completed for the corridor.

This contract will also include coordination with the Naples Botanical Garden with the plant selection for landscaping.
The City of Fort Myers will provide oversight during construction and installation.

(See Proposed Timeline below)

Commencement Date

Anticipated Summer 2024

Address

US 41 in the Cleveland CRA District

STATUS UPDATE

Send out to Bid

2/14/25
STATUS UPDATE

Final Permit Review & FDOT Approval ‐ February 7

4-6 weeks
STATUS UPDATE

90% CD’s ‐ 3rd Permit Plan Submittal to FDOT

12/27/24
STATUS UPDATE

60% CD’s ‐ 2nd Permit Plan Submittal to FDOT

11/15/24
STATUS UPDATE

Permit Review

4-6 weeks
STATUS UPDATE

30% CD’s ‐ 1st Permit Plan Submittal to FDOT

10/4/2024
STATUS UPDATE

City Review & Approve to Submit for Permit

10/1/2024 - 10/3/2024
STATUS UPDATE

Rvi Prepare 30% Construction Documents

8/30/2024 - 9/30/2024
STATUS UPDATE

Team Meeting to Review Design Development Presentation, Comments due August 26

8/19/24 - 8/23/24
STATUS UPDATE

Team Coordination with Naples Botanical Garden ‐ Preliminary Planting Design

August
STATUS UPDATE

RVi Design Development

7/22/24 - 8/16/2024
STATUS UPDATE

Team Meeting to Review SD, Comments due back by July 22

7/15/24 - 7/19/24
STATUS UPDATE

SD Package sent to team

7/5/24
STATUS UPDATE

RVi Inventory & Analysis/Schematic Design

4/1/24 - 4/19/24
STATUS UPDATE

Notice to Proceed

3/25/24
STATUS UPDATE

Team Kick Meeting

3/20/2024